top of page

20MVA


20MVA substation located at Bahay Libmanan Camarines Sur benefit libmanan, Cabusao and part of Pamplona. Its output will be 4 feeders in addition to the 10 feeders of coop. Cost is 48 million which includes lot substation and 69 KV lines contracted by Asiaphil Inc. project duration is 180 days lot area is 613sq.